15. Disconnection of Facility for Other Reasons
15.1 The Customer shall discontinue operation of the Facility and the Distributor may isolate or disconnect the Facility from the Distributor's distribution system, upon any of the following:
(a) termination of this Agreement in accordance with section 19;
(b) if the Customer's connection assets or the Facility are modified by the Customer in a manner contrary to section 8.1;
(c) during an emergency or where necessary to prevent or minimize the effects of an emergency;
(d) in accordance with section 31, 31.1 or 40(5) of the Electricity Act, 1998, other applicable law, the Code, the Distributor's Licence or the Distributor's Conditions of Service; or
(e) where required to comply with a decision or order of an arbitrator or court made or given under Schedule G.
15.2 In the event of disconnection under section 15.1(b), the Facility shall remain isolated or disconnected from the Distributor's distribution system until the connection process referred to in section 8.1 has been completed.
15.3 In the event of disconnection under section 15.1(c), the Distributor shall reconnect, or permit the reconnection of, the Facility to the Distributor's distribution system when it is reasonably satisfied that the emergency has ceased and that all other requirements of this Agreement are met.
15.4 In the event of disconnection under section 15.1(d) or 15.1(e), the Distributor shall reconnect, or permit the reconnection of, the Facility to the Distributor's distribution system when the Distributor is reasonably satisfied that the reason for the disconnection no longer exists, the Customer agrees to pay all Board-approved reconnection costs charged by the Distributor, and the Distributor is reasonably satisfied of the following, where applicable:
(a) the Customer has taken all necessary steps to prevent the circumstances that caused the disconnection from recurring and has delivered binding undertakings to the Distributor that such circumstances shall not recur; and
(b) any decision or order of a court or arbitrator made or given under Schedule G that requires a Party to take action to ensure that such circumstances shall not recur has been implemented and/or assurances have been given to the satisfaction of the affected Party that such decision or order will be implemented.
15.5 Where the Facility has been isolated or disconnected, each Party shall be entitled to decommission and remove its assets associated with the connection. Each Party shall, for that purpose, ensure that the other Party has all necessary access to its site at all Page | 10 reasonable times.
15.6 The Customer shall continue to pay for distribution services provided up to the time of isolation or disconnection of its Facility.
15.7 The Customer shall pay all reasonable costs including, but not limited to, the costs of removing any of the Distributor's equipment from the Customer's site, that are directly attributable to the isolation or disconnection of the Facility and, where applicable, the subsequent decommissioning of the Facility. The Distributor shall not require the removal of the protection and control wiring on the Customer's site.
15.8 While the Facility is isolated or disconnected, the Distributor shall not be required to convey electricity to or from the Facility.